New transformer installation completed to support upgraded electrical service for Buildings 76 and 80.
Primary cable pulling operations underway as part of the electrical infrastructure upgrade.
Trenching and conduit installation underway as part of the electrical system upgrade.

New transformer installation completed to support upgraded electrical service for Buildings 76 and 80.

Project Scope

This project involved comprehensive electrical infrastructure upgrades to Buildings 76 and 80, including demolition of existing power distribution systems and installation of new primary and secondary electrical service. The work included removal of outdated feeders, transformers, and panels, followed by installation of new feeders, transformer replacement, and upgraded distribution panels to support future facility needs. Interior and exterior lighting systems were also modernized with high-efficiency LED fixtures, along with the addition of new receptacles, switches, and controls to improve functionality and usability. In addition to electrical upgrades, the project included full site coordination and preparation, such as utility locates, permitting, erosion control, and site clearing. The team coordinated with the local utility provider for reconnection and ensured all work met applicable standards. Final activities included testing, as-built documentation, site restoration, and cleanup to return the area to pre-construction conditions while maintaining safety and compliance throughout the project lifecycle.

Key Features

  • Performed full electrical system upgrade for Buildings 76 and 80, replacing outdated infrastructure
  • Installed new primary and secondary feeders, transformer, and distribution panels
  • Upgraded interior lighting to high-efficiency LED high bays with zoned controls
  • Added exterior lighting, switches, and receptacles to improve building functionality
  • Coordinated utility reconnection with local power provider (KCPL)
  • Completed site preparation, including clearing, erosion control, and traffic management
  • Ensured code compliance and future capacity with upgraded electrical systems
  • Delivered full project closeout, including as-builts, site restoration, and safety measures

Project Details

CategoryElectrical Upgrade
LocationUndisclosed DoW Installation
CompletedQ3 2025
ClientU.S. Air Force

Explore More Projects

View our full portfolio of mission-critical construction projects.

All Projects